"You went above and beyond the call of duty with regard to researching various issues that came up during the course of construction. The information you gathered regarding these issues was most valuable in helping me make the decisions, keeping me on track from a timing standpoint...and under budget."
Thomas J. White, President
White Company
Our goal is to be responsible for as much of each project as possible. By opening your project to Construction Manager Advisor participation during the design development process, you are able to utilize our staff’s strength of working with the design team and local governmental agencies at the early stages of a project’s inception. And during construction, Richard K. Davis Construction Corporation prides itself in utilizing their own tradesmen who specialize in concrete, masonry, pre-engineered steel erection, carpentry, cabinetry and painting. Applying our capabilities to the task of coordinating as many phases of a project, from design and permitting through final inspections and certificate of completion, we minimize the unexpected and ensure a smooth, efficient, and timely building experience.
PRE-CONTRUCTION SCHEDULE CONTROL
Meet with governmental agencies to determine required procedures and key
submission dates
Review with design team members to determine realistic design completion goals
Create project Pre-Construction Control Schedule projections using Microsoft
Project Software
Identify on Pre-Construction Control Schedule critical milestones and permitting
submission dates
Transmit and review final Pre-Construction Control Schedule with team members
Review time line regularly at pre-arranged team conferences
Update Pre-Construction Control Schedule at the completion of each design phase
DURING CONSTRUCTION SCHEDULE CONTROL
Expand Construction Control Schedule after completion of 80% Construction
Documents utilizing Microsoft Project software
Identify critical path and other milestone dates on Construction Control Schedule
Review Construction Control Schedule with key subcontractors and suppliers /
update as necessary
Update Construction Control Schedule prior to each Job-Site Coordination Meeting
and at a minimum no less than monthly
Organize, schedule and conduct periodic Job-Site Coordination Meetings
Distribute and review updated Construction Control Schedule at each coordination
meeting
Provide penalty and/or incentive programs for timely completion of tasks by
subcontractors
CURRENT 10-YEAR TRACK OF SCHEDULE CONTROL
A review of our significant construction project’s track record on meeting contractual completion date obligations reveals that we secure Substantial Completion on or ahead of our target 90% of the time. Of those not completed on time, a majority were directly impacted by three major hurricanes during the 2004 and 2005 hurricane seasons.
Copyright ©2024 Richard K. Davis Construction Corp. All rights reserved